Locations Completed: 188
Timeframe: 1 day to 3 weeks
Completion Date: Ongoing since 2014
Partner Since: 2014
H.J. Martin and Son has provided fixture installations and other upgrades to 188 Burlington stores and counting since 2014.
Most projects are done in an open-store environment with H.J. Martin and Son upgrading one to three departments in each store. Work includes demolishing old fixtures, building, setting and profiling new fixtures. Additionally, if some departments need new carpet or wall patching, our team self-performs the work. We also manage electrical and lighting subcontractors.